PPR pipe hot melting apparatus using the methodAuthor:匿名 Source by: 本站原創(chuàng) Published by: 2015年1月26日 Viewed by: 22373 1 fixed welding device installed heating end, the welding device is placed in a frame, according to the requirements of die head heating pipe installation corresponding specifications, and with the inner six anglewrench, generally small in front, high on the back end.
2 switch on the power (note that the power supply must be provided with grounding protection wire), according to the corresponding models of machine instructions note indicator changes, until the welding device into the controlstate, can start operation.
3 pipe cutter for vertically cutting pipe, the pipe and pipe fittings and non rotating propulsion fusion splicer in the die, and operates according to the requirements. Heating time is reached immediately after the pipe and pipe fittings from the die head removed simultaneously, rapidly rotating homogeneous without directly inserted into thedesired depth, so that the formation of uniform flange joint.
Source: new pipe industry |